Bags needed (chosen size, with waste)
47 bags
Concrete to order
0.768 yd3
Concrete in one tube
3.142 ft3
Concrete per foot of tube height
0.785 ft3
All tubes, no waste
18.850 ft3
Concrete to order, cubic feet
20.735 ft3
Concrete to order, metric
0.587 m3
40 lb bags
70 bags
50 lb bags
56 bags
60 lb bags
47 bags
80 lb bags
35 bags
Weight of the concrete (no waste)
2,639 lb
Tube cross-section
0.785 ft2
Cost in bags
329.00 USD
Cost as ready-mix
126.71 USD
Starting tube size for the post (3 x width)
n/a
Starting tube size, metric
n/a

How the Sonotube Calculator Formula Works

A Sonotube is a round cardboard form, so the concrete inside is a cylinder. Its volume is the circle area, pi x (diameter / 2)2, times the height of the concrete. Multiply by the number of tubes, then by 1 plus your waste allowance.

Divide the cubic feet by the yield of one bag (0.30, 0.375, 0.45 and 0.60 cubic feet for 40, 50, 60 and 80 lb bags, from the QUIKRETE data sheet) and round up to whole bags. Divide by 27 to get cubic yards for a ready-mix order.

In inches and feet, a tube holds pi x (diameter in inches / 24)2 cubic feet per foot of height. A 12 inch tube holds 0.785 cubic feet per foot.

concrete = pi × (diameter / 2)2 × height × number of tubes
What goes in, what comes out
  • diameterin12Inside diameter of the tube. Nominal sizes can differ a little, so measure if it matters.
  • heightft4Height of concrete in the tube, including any part above ground.
  • tubesNumber of tubes (footings or piers).
  • yieldcu ftVolume one bag makes, from the bag label.
Bags needed (chosen size, with waste)
47
Values shown are from the worked example below
diameter
in
Inside diameter of the tube. Nominal sizes can differ a little, so measure if it matters.
height
ft
Height of concrete in the tube, including any part above ground.
tubes
n/a
Number of tubes (footings or piers).
yield
cu ft
Volume one bag makes, from the bag label.

Using the Sonotube Calculator

  1. Enter units

    Choose from Inches and feet, Centimetres and metres.

  2. Enter tube diameter (inches or cm)

    Type the figure you already have, then press Calculate.

  3. Enter concrete height per tube (feet or metres)

    Type the figure you already have, then press Calculate.

  4. Enter number of tubes

    Type the figure you already have, then press Calculate.

  5. Enter waste allowance (%)

    Type the figure you already have, then press Calculate.

  6. Enter bag size

    Choose from 40 lb bag, 50 lb bag, 60 lb bag, 80 lb bag.

  7. Enter yield per bag in cubic feet (0 = use label default)

    Type the figure you already have, then press Calculate.

  8. Enter price per bag (placeholder, enter yours)

    Type the figure you already have, then press Calculate.

  9. Enter ready-mix price per cubic yard (placeholder)

    Type the figure you already have, then press Calculate.

  10. Enter post width for a size hint (inches or cm, 0 to skip)

    Type the figure you already have, then press Calculate.

  11. Read the result

    Press Calculate to update the result. Until you do, the last result is dimmed and marked as out of date, so you always know which numbers belong to the values in the boxes.

A Real Worked Example

Six 12 inch tubes, each filled to a height of 4 feet. A 12 inch tube has a radius of 0.5 feet, so it holds pi x 0.52 = 0.785 cubic feet per foot. Four feet of height is 3.142 cubic feet in one tube.

Six tubes hold 18.850 cubic feet. With 10 percent waste the order is 20.735 cubic feet, or 0.768 cubic yards. A 60 lb bag yields 0.45 cubic feet, so 20.735 / 0.45 = 46.08, which rounds up to 47 bags. At a placeholder $7 a bag that is $329.00, against $126.71 for ready-mix at $165 a cubic yard, though a truck has a minimum load.

1
unit
imperial
2
diameter
12
3
height
4
4
count
6
5
waste
10
6
bagSize
60
7
bagYield
0
8
pricePerBag
7
9
pricePerYard
165
10
postWidth
0
This calculator returns47bags0.768orderCuYd3.142perTubeFt30.785cuFtPerFoot18.85totalFt320.735orderFt30.587orderCuM70bags4056bags5047bags6035bags802639weightLb0.785areaSqFt329bagCost126.71readyMixCost

Nine deck footings: 16 inch tubes, 5 feet tall

Nine 16 inch tubes at 5 feet. The radius is 8 inches, so one foot of tube holds 1.396 cubic feet and one 5 foot tube holds 6.981. Nine tubes hold 62.832 cubic feet.

With 10 percent waste the order is 69.115 cubic feet, or 2.560 cubic yards. In 80 lb bags (0.60 cubic feet each) that is 115.19 bags, rounded up to 116. The concrete weighs about 8,796 lb. Deck footings carry structural loads, so the size and depth come from the deck design or your building inspector, not from this estimate.

unit: imperialdiameter: 16height: 5count: 9waste: 10bagSize: 80bagYield: 0pricePerBag: 9pricePerYard: 165postWidth: 0116bags2.56orderCuYd6.981perTubeFt31.396cuFtPerFoot62.832totalFt369.115orderFt31.957orderCuM231bags40185bags50154bags60116bags808796weightLb1.396areaSqFt1044bagCost422.37readyMixCost

Four 8 inch tubes, 3 feet tall, 40 lb bags

An 8 inch tube has a radius of 4 inches, so it holds 0.349 cubic feet per foot, and a 3 foot tube holds 1.047. Four tubes hold 4.189 cubic feet and the order with 10 percent waste is 4.608 cubic feet (0.171 cubic yards).

A 40 lb bag yields 0.30 cubic feet, so that is 15.36 bags, rounded up to 16. For this size, small bags are easy to carry and the total is a manageable 640 lb of mix.

unit: imperialdiameter: 8height: 3count: 4waste: 10bagSize: 40bagYield: 0pricePerBag: 5.5pricePerYard: 165postWidth: 016bags0.171orderCuYd1.047perTubeFt30.349cuFtPerFoot4.189totalFt34.608orderFt30.13orderCuM16bags4013bags5011bags608bags80586weightLb0.349areaSqFt88bagCost28.16readyMixCost

Metric: five 30 cm tubes, 1.2 m tall

With the units set to metric, enter the diameter in centimetres and the height in metres. A 30 cm tube has a radius of 0.15 m, so it holds pi x 0.152 × 1.2 = 0.0848 cubic metres, or 2.995 cubic feet.

Five tubes with 10 percent waste need 0.467 cubic metres (16.48 cubic feet, 0.610 cubic yards). In 60 lb bags that is 37 bags. At $200 per cubic yard the ready-mix cost is $122.04.

unit: metricdiameter: 30height: 1.2count: 5waste: 10bagSize: 60bagYield: 0pricePerBag: 7pricePerYard: 200postWidth: 037bags0.61orderCuYd2.995perTubeFt30.761cuFtPerFoot14.977totalFt316.475orderFt30.467orderCuM55bags4044bags5037bags6028bags802097weightLb0.761areaSqFt259bagCost122.04readyMixCost

Two 24 inch tubes, 6 feet tall, with a 6x6 post

Two 24 inch tubes at 6 feet hold 3.142 cubic feet per foot, or 18.850 cubic feet each and 37.699 for both. With 5 percent waste the order is 39.584 cubic feet, which is 1.466 cubic yards and 88 bags of 60 lb mix.

Enter the post width, 5.5 inches for a 6x6, and the calculator shows a starting tube size of 3 × 5.5 = 16.5 inches. That points to an 18 inch tube, so the 24 inch tube here is generous. The size is a rule of thumb, and the footing design decides.

unit: imperialdiameter: 24height: 6count: 2waste: 5bagSize: 60bagYield: 0pricePerBag: 7pricePerYard: 165postWidth: 5.588bags1.466orderCuYd18.85perTubeFt33.142cuFtPerFoot37.699totalFt339.584orderFt31.121orderCuM132bags40106bags5088bags6066bags805278weightLb3.142areaSqFt616bagCost241.9readyMixCost16.5suggestedDiaIn41.9suggestedDiaCm

Using your own bag yield of 0.5 cubic feet

Three 12 inch tubes, 4 feet tall, with 10 percent waste need 10.367 cubic feet. Suppose your bag label gives a yield of 0.5 cubic feet. Type 0.5 in the yield box and the calculator divides by that: 10.367 / 0.5 = 20.73, rounded up to 21 bags.

The 40, 50, 60 and 80 lb counts (35, 28, 24 and 18) still use the standard yields so you can compare with other bag sizes.

unit: imperialdiameter: 12height: 4count: 3waste: 10bagSize: 60bagYield: 0.5pricePerBag: 7pricePerYard: 165postWidth: 021bags0.384orderCuYd3.142perTubeFt30.785cuFtPerFoot9.425totalFt310.367orderFt30.294orderCuM35bags4028bags5024bags6018bags801319weightLb0.785areaSqFt147bagCost63.36readyMixCost

What Else to Know

How to calculate concrete for a Sonotube

A Sonotube is a round fibre form, so the concrete inside is a cylinder. The volume of a cylinder is pi times the radius squared times the height, as set out in the [Wikipedia article on the cylinder](https://en.wikipedia.org/wiki/Cylinder). With the diameter in inches and the height in feet, one foot of tube holds pi x (diameter / 24)2 cubic feet.

Sonotube formula: pi times radius squared times height gives the concrete in one tube, then bags and cubic yards

A 12 inch tube holds 0.785 cubic feet per foot. A 4 foot tube holds 3.142 cubic feet, and six of them hold 18.85 cubic feet before waste. Divide by 27 for cubic yards. The calculator also gives the cross-section area in square feet, which is the same number as the cubic feet per foot, and the volume in cubic metres.

Worked example: six 12 inch Sonotubes 4 feet tall need 20.73 cubic feet, which is 47 bags of 60 lb mix

The table below lists the concrete per foot for diameters from 6 to 36 inches. The numbers grow with the square of the diameter, so doubling the diameter quadruples the concrete. A 24 inch tube holds four times as much as a 12 inch one.

Bar chart of cubic feet of concrete per foot of height for Sonotube diameters from 6 to 36 inches

Sonotube sizes and what the manufacturer's chart says

The Sonoco data sheet for the Sonotube Builder's Tube concrete forms lists tube diameters of 6, 8, 10 and 12 inches in standard lengths of 4, 8 and 12 feet. It prints a chart of cubic feet of concrete per foot of height: 0.20, 0.35, 0.55 and 0.80, and it notes that diameter sizes are nominal and should be measured if critical.

Bar chart comparing the Sonoco chart with exact cylinder volume per foot for 6, 8, 10 and 12 inch tubes

The exact cylinder volumes are 0.196, 0.349, 0.545 and 0.785 cubic feet per foot. The chart rounds those figures up, by up to 2 percent, which is useful as a small built-in margin. The calculator uses the exact volume and gives you your own waste allowance, so you can see both numbers and choose.

Larger tubes, from 14 inches up to 36 inches and more, are commonly sold for column and pier forms, and the same circle formula applies. Sizes and wall strength vary by supplier, so check the form maker's data for the size you plan to buy.

How many bags of concrete for a 12 inch Sonotube?

For a 12 inch tube, each foot of height needs 0.785 cubic feet. The Sonoco chart says that is 1 1/3 bags of 80 lb mix or 2 bags of 60 lb mix per foot, while the exact volume divided by the label yield gives 1.31 bags of 80 lb and 1.75 bags of 60 lb.

Bar chart of bags per foot of height for a 12 inch Sonotube using 40, 50, 60 and 80 lb concrete bags

A 4 foot tube then holds 3.14 cubic feet, or 5.24 bags of 80 lb mix and 6.98 bags of 60 lb mix. The yields come from the QUIKRETE Concrete Mix No. 1101 data sheet: 0.30 cubic feet for a 40 lb bag, 0.375 for 50 lb, 0.45 for 60 lb and 0.60 for 80 lb. If your brand prints a different yield, type it into the yield box.

Bags are rounded up for the whole job, not per tube, so the total for six tubes is 47 bags of 60 lb mix, not six times a rounded single-tube number.

Bar chart of 60 lb bags for 1 to 20 twelve inch Sonotubes 4 feet tall with 10 percent waste

Which tube size for a post or a footing?

For a post set in concrete, a handy starting size is 3 times the post width. The QUIKRETE data sheet for setting posts states that the hole diameter should be 3 times the post diameter. A 4x4 post (3.5 inches actual) gives 10.5 inches, so a 12 inch tube. A 6x6 post (5.5 inches) gives 16.5 inches, so an 18 inch tube. Enter the post width in the calculator and it shows the starting size. This is a rule of thumb, not a design.

Bar chart of cubic feet of concrete in one 4 foot Sonotube for diameters from 8 to 24 inches

For a footing under a deck, shed or building column, the diameter depends on the load, the soil bearing capacity and local code. That is an engineering decision and varies from site to site. This calculator tells you how much concrete the size you choose will take. It does not tell you what size is safe. Have deck and structure footings designed or checked by an engineer or your building inspector.

The Sonoco sheet lists decks, fence and lamp posts, swing sets, mailbox posts and basketball goals among the uses of the Builder's Tube.

Placing concrete in the tube: what the manufacturer says

The Sonoco sheet gives the following steps for the Builder's Tube. Dig the hole to the desired depth and place the tube in the hole, filling around the outside to secure it. If the tube extends more than 2 feet above ground, add a collar or wooden frame with side braces. The tube should be dry before it is filled, and it is single-use. The sheet says to erect all the tubes for the job in advance so the pour can be done at once.

It cautions against mechanical vibration, and says the tube should remain stationary until the concrete sets. The form is designed for below ground-line placement, but it can be used up to 3 feet above ground. The tubes are meant to stay in place, and if you want to strip one, use a release agent before pouring and remove the form after about 24 hours of cure by cutting it vertically.

The tube height in the calculator is the height of concrete, so include the part above ground if there is any. For a 5 foot tube set 4 feet deep, the tube height is 5 feet.

Depth, frost and why the height is your decision

The height of each tube comes from the footing depth and any length above ground, not from the calculator. The [frost line](https://en.wikipedia.org/wiki/Frost_line) is the depth to which groundwater in soil is expected to freeze. The Wikipedia article explains that building codes take frost depth into account because of frost heaving, and that foundations are generally built below the frost depth. Your local building department gives the figure that applies to you.

Bar chart of the weight in pounds of one 4 foot tube filled with concrete, for diameters from 8 to 24 inches

Many jurisdictions also set a minimum footing size and depth for decks and porches, and ask for an inspection before the concrete is poured. Call your building department before you dig, and call the utility locating service so buried lines are marked.

Once you have the diameter and height from your plans, enter them with the number of tubes. The calculator returns the cubic feet, cubic yards, cubic metres, bags of each size and the weight of the concrete. A 12 inch tube 4 feet tall holds 440 lb of concrete at 140 pounds per cubic foot, so each tube is heavy once filled.

Bags or ready-mix, rebar and what to read next

For a few tubes, bagged mix is practical. For nine 16 inch tubes at 5 feet you would need 116 bags of 80 lb mix, about 9,280 lb to move, against 2.56 cubic yards of ready-mix. Ready-mix is priced per cubic yard and often has a minimum load and a delivery fee, so enter both prices and compare. The prices in the calculator are placeholders.

Rebar, ties and anchor bolts take a little space but they are small. The calculator does not size reinforcement. That belongs in the plans, or with an engineer or inspector. Leave the reinforcement inside your waste allowance.

If you want gravel in the bottom of the hole, the gravel calculator turns a depth and an area into cubic yards. For block piers instead of poured ones, the CMU block calculator counts the blocks, and the stone calculator covers decorative stone around the footings.

Limits of the Sonotube estimate: nominal sizes, waste, bag yields, no footing design and professional checks

This is an estimate. Follow the form maker's directions, the bag label and your local building code, and have a professional confirm structural footings.

Reference Tables

Cubic feet of concrete per foot of tube height by inside diameter (pi x r^2), with cubic yards per 10 feet of height
Tube diameterCubic feet per footCubic yards per 10 ftCross-section (sq ft)Litres per foot
6 in0.1960.0730.1965.6
8 in0.3490.1290.3499.9
10 in0.5450.2020.54515.4
12 in0.7850.2910.78522.2
14 in1.0690.3961.06930.3
16 in1.3960.5171.39639.5
18 in1.7670.6541.76750.0
20 in2.1820.8082.18261.8
24 in3.1421.1643.14289.0
30 in4.9091.8184.909139.0
36 in7.0692.6187.069200.2
The Sonotube Builder's Tube chart (cubic feet per foot of height) beside the exact cylinder volume
Nominal diameterChart (cu ft per ft)Exact pi x r^2 (cu ft per ft)Chart is higher byChart 80 lb bags per ftExact 80 lb bags per ft
6 in0.200.1961.9 %1/30.33
8 in0.350.3490.3 %3/50.58
10 in0.550.5450.8 %10.91
12 in0.800.7851.9 %1 1/31.31
Bags per foot of tube height by diameter and bag size (exact, before waste and rounding)
Tube diameter40 lb bags50 lb bags60 lb bags80 lb bags
6 in0.650.520.440.33
8 in1.160.930.780.58
10 in1.821.451.210.91
12 in2.622.091.751.31
14 in3.562.852.381.78
16 in4.653.723.102.33
18 in5.894.713.932.95
20 in7.275.824.853.64
24 in10.478.386.985.24
30 in16.3613.0910.918.18
36 in23.5618.8515.7111.78
Cubic feet of concrete in one tube by diameter and height
Tube diameter2 ft3 ft4 ft5 ft6 ft
8 in0.701.051.401.752.09
10 in1.091.642.182.733.27
12 in1.572.363.143.934.71
16 in2.794.195.596.988.38
18 in3.535.307.078.8410.60
24 in6.289.4212.5715.7118.85
Several 12 inch tubes 4 feet tall, with 10 percent waste, in 60 lb bags
TubesConcrete (cu ft)Concrete (cu yd)60 lb bags80 lb bags
13.460.12886
26.910.2561612
413.820.5123124
620.730.7684735
1034.561.2807758
2069.122.560154116
Starting tube size for a post: 3 times the post width, then the next common diameter (a rule of thumb, not a design)
PostActual width (in)3 x width (in)Next common tube (in)Concrete per foot (cu ft)
4x43.5010.50120.785
6x65.5016.50181.767
8x87.2521.75243.142
Weight of one filled tube, 4 feet tall, at 140 pounds per cubic foot (the unit weight on the QUIKRETE data sheet)
Tube diameterConcrete (cu ft)Weight (lb)Weight (kg)
8 in1.4019589
10 in2.18305139
12 in3.14440200
16 in5.59782355
18 in7.07990449
24 in12.571,759798
Metric tubes: concrete per metre of height by inside diameter
Diameter (cm)Cubic metres per metreLitres per metreCubic feet per footDiameter (in)
150.017717.70.1905.9
200.031431.40.3387.9
250.049149.10.5289.8
300.070770.70.76111.8
400.1257125.71.35315.7
500.1963196.32.11319.7
600.2827282.73.04323.6
Bags against delivered ready-mix for 9 tubes, 16 inch by 5 feet, 10 percent waste (placeholder prices, replace with yours)
OptionPrice usedQuantityCost
80 lb bags$9.00 per bag116 bags$1,044.00
80 lb bags$7.50 per bag116 bags$870.00
Ready-mix$165 per cu yd2.56 cu yd$422.37
Ready-mix$200 per cu yd2.56 cu yd$511.96
Waste allowance on six 12 inch tubes, 4 feet tall (60 lb bags)
WasteConcrete to order (cu ft)60 lb bagsExtra bags against 0 percent
0 %18.85420
5 %19.79442
10 %20.73475
15 %21.68497
20 %22.62519
The six worked examples on this page at a glance
ExampleTubesConcrete to order (cu ft)Cubic yardsBags
12 in tubes, 4 ft620.730.76847 × 60 lb
16 in tubes, 5 ft969.122.560116 × 80 lb
8 in tubes, 3 ft44.610.17116 × 40 lb
Metric 30 cm, 1.2 m516.480.61037 × 60 lb
24 in tubes, 6 ft239.581.46688 × 60 lb
12 in, bag yield 0.5310.370.38421 × 0.5 cu ft

Frequently Asked Questions About the Sonotube Calculator

How do I calculate Sonotube size?

Match the tube to the load or the post. For a post, a starting size is 3 times the post width: a 4x4 (3.5 inches) gives 10.5 inches, so a 12 inch tube. For a footing under a column or deck post, the diameter comes from the load and soil, which an engineer or inspector sets. The calculator then gives the concrete for the size you enter.

How many bags of concrete do I need for a 12 sonotube?

A 12 inch tube holds 0.785 cubic feet per foot of height. That is 1.31 bags of 80 lb mix or 1.75 bags of 60 lb mix per foot. A 4 foot tube takes 3.14 cubic feet, about 6 bags of 80 lb or 7 of 60 lb, before any waste allowance.

How many Sonotubes do I need?

You need one tube for every footing or pier in your plan. A deck has one under each post, and a fence gate or shed often has four to six. Count the footings from your plans or the building inspector's layout, then enter that number. The calculator multiplies the volume for one tube by the count. Spacing and footing size come from the design, not from this tool.

How big of a Sonotube for a 6x6 post?

A 6x6 post is 5.5 inches wide, so the 3 times rule gives 16.5 inches, and the next common size up is an 18 inch tube. That holds 1.77 cubic feet per foot. Some people use a 12 inch tube for a light post, but check the plans, load, and local code, because the footing size is a design question.

How do you calculate the concrete in a Sonotube?

Use the cylinder volume: pi x (diameter / 2)2 x height. For a 12 inch tube 4 feet tall, that is pi x 0.52 × 4 = 3.142 cubic feet. Multiply by the number of tubes, add waste, and divide by the bag yield or by 27 for cubic yards. Enter the real inside diameter, since nominal sizes can differ a little.

How much concrete is in a 12 inch Sonotube per foot?

A 12 inch tube holds pi x 0.52 = 0.785 cubic feet per foot of height. The Sonotube Builder's Tube chart prints 0.80, which rounds the exact volume up slightly. At 10 feet the tube holds 7.85 cubic feet, or 0.291 cubic yards.

How many cubic yards in a 14 inch Sonotube?

A 14 inch tube holds 1.069 cubic feet per foot, which is 0.0396 cubic yards per foot. A 4 foot tube is 4.28 cubic feet, or 0.158 cubic yards. Twelve of them with 15 percent waste come to 2.19 cubic yards.

How much concrete for a 16 inch Sonotube?

A 16 inch tube holds 1.396 cubic feet per foot of height. A 5 foot tube holds 6.98 cubic feet, which is 11.6 bags of 80 lb mix, so 12 bags per tube before waste. Nine such tubes with 10 percent waste need 116 bags of 80 lb mix.

How do I get the Sonotube square feet?

The cross-section area is pi x r2. A 12 inch tube has 0.785 square feet, and a 24 inch tube has 3.142. The same number is the cubic feet of concrete per foot of height, because one foot of height times the area is the volume. Use it for the footprint or the bearing area of the footing.

How tall should a Sonotube be?

The height is the footing depth plus any length that stands above ground. Footing depth comes from your frost depth, soil and plans. Wikipedia explains that foundations are generally built below the frost depth, and your building department sets the local figure. The Sonoco sheet says the Builder's Tube is for below-ground placement but can go up to 3 feet above ground line.

Can a Sonotube stand above ground?

Yes, within limits. The Sonoco Builder's Tube data sheet says the form is designed for below ground-line placement but can be used up to 3 feet above ground line for extra support, and minimal bracing is needed above 2 feet. If the tube extends more than 2 feet above ground, it calls for a collar or wooden frame and side braces. The data sheet also says the tube must stay dry before filling.

Do I need rebar in a Sonotube?

That depends on the design. Many footings and piers are reinforced, but this calculator does not size rebar or give structural design. Your plans, an engineer or the building inspector decide whether bars, ties or anchor bolts go in and how big they are. Reinforcement takes up a little space, but the volume is small, so leave it in your waste allowance.

Can I use a mechanical vibrator in a Sonotube?

Not with the Builder's Tube. The Sonoco data sheet cautions against mechanical vibration when placing concrete in the form, and says the tube should remain stationary until the concrete sets. Instead, fill in lifts and tamp or rod the concrete by hand to remove air pockets. Follow the form maker's directions for the product you buy.

Can I remove the Sonotube after the concrete sets?

The Builder's Tube is single-use and designed to stay in place. If you want to strip it above ground, the Sonoco sheet says to use a release agent before pouring, and remove the form as soon as possible after about 24 hours of curing by cutting it vertically with a knife or saw. No warranty is extended on the finished surface.

How much does a filled Sonotube weigh?

At 140 pounds per cubic foot, the unit weight on the QUIKRETE data sheet, a 12 inch tube 4 feet tall weighs about 440 pounds, and a 24 inch tube 4 feet tall about 1,759 pounds. The calculator shows the total weight of the concrete for all of your tubes. Plan how the tubes will be filled and who will lift what.

Should I buy bags or order ready-mix?

For a few small tubes bags are practical. For 2.56 cubic yards, like the nine 16 inch tubes above, you would carry 116 bags of 80 lb mix, which is a lot of lifting. Ready-mix is priced by the cubic yard, often with a minimum load, so enter both prices in the calculator and compare. Check the delivery access, since a truck needs room.

How much waste should I add for tubes?

Allow 5 to 10 percent for spill, uneven tube walls and a slightly deeper hole. Ten percent on six 12 inch tubes 4 feet tall adds 5 bags to the order. Cardboard tubes can bulge a little under wet concrete, and nominal diameters are not exact, so measure your tube if the size is critical.

Can I use the calculator for any round form tube?

Yes. Enter the inside diameter and the height of the concrete, in inches and feet or centimetres and metres. The Sonotube Builder's Tube comes in 6, 8, 10 and 12 inch sizes according to the Sonoco sheet, and other round forms come in larger diameters. The result works for any round tube, whatever its brand.

Does the 12-inch Sonotube calculator differ for metric?

No, only the units. Switch to metric to enter the diameter in centimetres and the height in metres. A 30 cm tube 1.2 m tall holds 0.0848 cubic metres, which is 85 litres. Five of them with 10 percent waste come to 0.467 cubic metres.

How deep should the footing under a tube go?

The hole depth comes from your frost depth, the soil and the plans, not from this calculator. Foundations are generally built below the frost depth, as the Wikipedia frost line article notes, because frost heave can move them. Your building department gives the local figure, and deck or structure footings should be sized by a designer or inspector. Enter the tube height that results.

References

  1. [1] Sonoco Products Company. “Sonotube Builder's Tube concrete forms: sizes, concrete per foot of height, placing and stripping.” Sonoco. Accessed 2026-10-07.
  2. [2] The QUIKRETE Companies. “Concrete Mix, Product No. 1101: product data sheet (bag sizes, yields and unit weight).” QUIKRETE. Accessed 2026-10-07.
  3. [3] Wikipedia contributors. “Cylinder (geometry): volume formula.” Wikipedia. Accessed 2026-10-07.
  4. [4] Wikipedia contributors. “Frost line.” Wikipedia. Accessed 2026-10-07.